Lindian Resources Limited (ASX: LIN) says its Kangankunde Rare Earths Project in Malawi is still on schedule to deliver first monazite concentrate in December 2026. The update came in an October 15, 2026, release distributed via PRNewswire, backed by a longer filing with the Australian Securities Exchange.
Highlights
- Lindian Resources Limited (ASX: LIN) says its Kangankunde Rare Earths Project in Malawi remains on schedule for first monazite concentrate in December 2026.
- Ore stockpiles rose to approximately 149,000 tonnes, up about 24,000 tonnes (19%) from September, a figure the company says is derived from its existing Ore Reserve estimates.
- The update covers construction and readiness only; no new resource, reserve, or grade figures were released, and site power-up is still pending.
December is the month Lindian hopes to stop being a developer and start being a producer. Plenty of junior miners never make that jump.
Where the Build Stands
Most of the heavy equipment is in. The regrind mill, which crushes ore finer so the valuable grains can be pulled out, is fully installed. Structural steel in the wet high-intensity magnetic separation (WHIMS) and MGS areas is about 90% complete. The shaking tables, which use vibration and water to sort heavy mineral grains from lighter waste, are at roughly 80%.
Power is the next gate. The 33kV overhead line now reaches the transformer yard, and both 1,250 kVA plant transformers are back on site after passing factory acceptance testing. Lindian is targeting site energization for the first week of November. Until the power is on, motors can’t be tested and the control systems can’t go live.
The tailings storage facility and water supply are both slated for completion in November, ahead of the first ore being fed into the plant.
Ore Is Piling Up
The mine is running ahead of the plant. Roughly 149,000 tonnes of ore now sit on the run-of-mine (ROM) pad, the staging area where mined rock waits to be processed. In September, that figure was about 125,000 tonnes. Crews have also started drilling from the top of the hill for the first time, opening new mining faces.
One caveat on that tonnage. Lindian says it is derived from the company’s existing Ore Reserve estimates, but those estimates aren’t restated in this update. Nor does the filing name a Competent Person, the technical professional who signs off on estimates under Australia’s JORC Code (the counterpart to Canada’s NI 43-101). The company instead confirms that its previously reported technical information hasn’t materially changed.
From Builders to Operators
The first plant supervisor and two control room operators are on the payroll, with more staff due in early November. Operator training has started. Contracts for rail transport, freight forwarding, and product sampling are close to signing.
“Kangankunde is in the final stretch of construction,” Executive Director Zac Komur said. “Our target is clear: first monazite concentrate in December.”
Why Monazite Matters
Monazite is a phosphate mineral that carries rare earth elements, including neodymium and praseodymium (NdPr). Those two metals are key ingredients in the permanent magnets inside electric vehicle motors and wind turbines. Lindian says Kangankunde will produce a concentrate grading 55% total rare earth oxides (TREO).
China dominates rare earth processing today, so any new supply chain built outside it tends to draw interest from Western manufacturers and governments. Lindian is trying to build one. It has a funding and offtake partnership with Iluka Resources, announced in August 2025. It also owns the SARECO processing facility in Kazakhstan, and in September 2026 it signed a 10-year offtake deal with French processor Carester covering heavy rare earth products from that plant.
What Comes Next
Commissioning is where mine schedules most often slip, and Lindian hasn’t reached it yet. Power-up in early November is the first real checkpoint. First ore through the plant follows.
The company describes Stage 1 as fully funded, pointing to an A$91.5 million institutional placement in August 2025 and another A$100 million placement in April 2026. A Stage 2 Definitive Feasibility Study, aimed at expanding production, is running in parallel.
Sources
Editorial Disclosure
This article is based on a corporate press release issued by Lindian Resources Limited on October 15, 2026, and distributed via PRNewswire, together with the company’s accompanying ASX announcement dated October 16, 2026. Securities discussed: Lindian Resources Limited (ASX: LIN). Mining Markets Report has not received compensation from Lindian Resources, its management, investor relations representatives, or any third party for the creation of this specific coverage. No staff member, principal, or affiliate of Mining Markets Report holds a position, option, or interest in this security as of the publication date. The ore stockpile tonnage cited is derived, according to the company, from previously reported JORC Ore Reserve estimates that were not restated in this release and have not been independently verified by Mining Markets Report. Statements regarding the timing of site energization, commissioning, first monazite concentrate production, offtake arrangements, and Stage 2 development are forward-looking statements. They are subject to construction, commissioning, operational, logistical, market, and regulatory risks; actual outcomes and timing may differ materially. Mining stocks, including development-stage companies that have not yet reached commercial production, carry a high degree of financial risk and can result in the total loss of invested capital. This overview is published strictly for informational, news-reporting, and educational market context purposes only. It does not constitute an investment recommendation, endorsement, or professional financial, legal, or tax advice.
For further details regarding our editorial independence, publishing policies, and full risk disclaimers, please see our full Terms & Disclaimers Page